Aerial Views of the Manors at Central Park Condominiums, 2002 through 2017
[source: Google Earth]



April 29, 2002

This portion of the vacant infield of the Packard test track is the future site of the Manors at Central Park; construction started in late 2003.

2002-4-29_aerial.jpg (1613x911; 262577 bytes)


March 30, 2005 

The first units were sold in late July of 2004; the sales model is at the corner of Lexington South and West Broadway across from the retention pond; the builder's
construction trailer is located on Lexington West near the lower left corner of the photo.

2005-3-30_aerial.jpg (1604x918; 471287 bytes)


August 1, 2005

2005-8-1_aerial.jpg (1612x898; 302684 bytes)


August 27, 2005

2005-8-27_aerial.jpg (1615x905; 253718 bytes)


August 3, 2006

The duplex on Lexington West just south of the construction trailer is complete and will soon become the new sales model.

2006-8-3_aerial.jpg (1614x905; 338995 bytes)


June 29, 2007

Five duplexes have been completed in the 11 months since the previous photo was taken and no new basements are awaiting framing.  
The market is slowing and the builder is having financial problems.

2007-6-29_aerial.jpg (1614x911; 461759 bytes)


May 9, 2010

The original builder has been out of business since early 2008 and the remaining unsold units were finished and marketed by a second builder on behalf of the original
project lender.  The lots for Units 1-14 were purchased by that second builder in 2009 and since then, 4 of them have been completed, along with Unit 123 on Regent.

2010-5-9_aerial.jpg (1610x908; 468803 bytes)


June 21, 2011

More than a year later, only 2 more Units have been constructed (Units 2 and 4).

2011-6-21_aerial.jpg (1614x909; 199301 bytes)


April 11, 2015

Nearly 4 years later, all of single detached  Units 1-14 have been completed and the second builder is out of the picture. A third builder has just purchased the
remaining 47 vacant Units and the basement for duplex Units 152-153 has just been dug.

2015-4-11_aerial.jpg (1611x915; 402721 bytes)


April 13, 2016

One year later, 7 new duplex Units are completely framed and construction is underway on 4 more new Units, including the one on Lexington West 
which will become the third builder's sales model.

2016-4-13_aerial.jpg (1610x906; 402183 bytes)


April 7, 2017

The basements were dug later that month for the 4 remaining duplex Units.  As of Sept. 27, 2017, only the southern-most duplex had not been framed.

2017-4-7_aerial.jpg (1595x916; 411663 bytes)