Information regarding the demolition of the former Ford/Visteon/ACH Trim Plant located in Shelby Township, MI


Building Demolition



The former Ford/Visteon/ACH plant, looking southeast from the corner of 23 Mile and Mound Roads (June 28, 2012).
Click here for a close-up view from a little farther south along Mound Rd.


The former Ford/Visteon/ACH plant, looking southeast from the corner of 23 Mile and Mound Roads (May 3, 2012).

An aerial view of the Visteon parcel, which is outlined in red.
Demolition started on April 28, 2012 beginning with Building #16 (outlined in blue).
Click here to launch an interactive aerial view using Google Maps.

On May 25, 2011, the Shelby Twp. Planning Commission approved a demolition permit for the buildings on the former Visteon site, provided that the petitioner (Indiana Metals, LLC) agreed to follow 32 conditions, which can be read here in their entirety: Page 1 | Page 2

Condition #1 was a point of contention that took almost one year to resolve. The petitioner felt it was excessive while the township wanted a financial guarantee that the petitioner would complete all of the demolition, including the final phases of removing all underground utilities, concrete floors and foundations. Eventually an agreement was reached whereby the proceeds from the sale of the valuable recyclables recovered from the demolished structures (approx. $2.5 million) would be placed in escrow and held there until the final phases of the demolition project (which generate little in the way of recycling value) are completed.

Indiana Metals has hired the following local companies to work on this project:

  • BDS Environmental - provides project oversight, determines demolition sequence, performs asbestos removal, monitors air quality, interfaces with MDEQ

  • Blue Star, Inc. - complete demolition

  • Shelby Underground - on-site processing of recyclables

Indiana Metals finally received their permit and demolition work began on Saturday, April 28, 2012, starting with Building #16 and working generally northward.

BDS Environmental collects air samples during each work day in order to measure airborne lead levels at the point of demolition and at points both upwind and downwind from the demolition activities. The purpose of this air monitoring is to insure that the level of airborne lead dust in work areas does not exceed the OSHA action level of 30 micrograms of lead per cubic meter of air. The air sampling is analyzed weekly and an updated report is sent to Indiana Metals with a copy also going to Fazal Khan & Associates, the Consulting Engineers for Shelby Township. A copy of the updated report is forwarded weekly by Mr. Kahn to the webmaster for publication here. So far, none of the air samples have contained measurable levels of airborne lead. Click on the link below to read the latest report (PDF file format, approx. 4 MB):

Sampling and Analysis of Airborne Lead Dust - April 28 through May 8, 2012
(to date, all air samples have contained less than 1.0 micrograms of lead per cubic meter of air)


VISUAL PROGRESS REPORT
(all photos by Mike Grobbel)

Panorama of the eastern side of the remaining northerly buildings as they appeared on Aug. 31, 2012 (click on photo to view full size, 2.8 MB).
The only remaining above-ground structures are the Curtiss-Wright jet engine test cells (left), portions of the office building along Mound Rd (not visible but behind the test cells) and the powerhouse (right). The original Packard transmission building (the building that was closest to the Mound and 23 Mile Rd. intersection) was constructed out of reinforced concrete and has been reduced to dusty rubble which is not being kept properly wetted down as it is being processed for removal.
This image shows a large cloud of dust that was being blown about by the wind at the time this panorama was being taken. A complaint was registered with the Shelby Twp. Consulting Engineer, asking him to enforce Condition # 23 of the building demolition permit which states "All rubbish and debris shall be kept thoroughly wetted down to prevent dust and dirt from rising into the air."

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on Aug. 11, 2012 (click on photo to view full size, 2.0 MB).

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on July 24, 2012 (click on photo to view full size, 2.1 MB).

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on July 12, 2012 (click on photo to view full size, 2.2 MB).

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on July 6, 2012 (click on photo to view full size, 2.3 MB; click here for a detailed enlargement of the exposed portions of the Curtiss-Wright jet engine test cells):

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on June 27, 2012 (click on photo to view full size, 1.9 MB; click here for a detailed enlargement, 0.6 MB):

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on June 21, 2012 (click on photo to view full size, 2.2 MB; click here for a detailed enlargement, 0.6 MB):

 

Panorama of the eastern side of the remaining northerly buildings as they appeared on June 14, 2012 (click on photo to view full size, 2.3 MB; click here for a detailed enlargement, 1.3 MB):

 

Panorama of the eastern side of all the buildings as they appeared on June 14, 2012 (click on photo to view full size, 9.2 MB):

 

Panorama of the eastern side of all the buildings as they appeared on June 7, 2012 (click on photo to view full size, 9.1 MB):

 

Panorama of the eastern side of all the buildings as they appeared on May 31, 2012 (click on photo to view full size, 8.1 MB):

 

Panorama of the eastern side of all the buildings as they appeared on May 24, 2012 (click on photo to view full size, 7.9 MB):

 

Panorama of the eastern side of all the buildings as they appeared on May 17, 2012 (click on photo to view full size, 8.5 MB):

 

Panorama of the eastern side of all the buildings as they appeared on May 10, 2012 (click on photo to view full size, 9.1 MB):

 

Panorama of the eastern side of all the buildings as they appeared on May 3, 2012 (click on photo to view full size, 8.3 MB):

 

This is what was left of Building #16 as of noon on May 3, 2012 (click on photo to view full size, 2.0 MB):

 

Mike Grobbel's notes from the meetings of May 25, 2011, March 12, 2012 and May 2, 2012


Return to:
Central Park Master Association | Manors at Central Park Condo Association

Visit grobbel.org


Last updated: 26 March 2014

Webmaster:

Mike Grobbel (about me) (contact)
49997 Lexington Ave. East, Shelby Twp., MI 48317
President - Board of Directors,
Manors at Central Park Condo Association